Transmission
Lines
Tingla Hub Substation
Jade Consult, in association with POWERGRID Corporation of India Ltd., is engaged in the development of high-capacity transmission infrastructure designed to strengthen the Integrated Nepal Power System (INPS). The transmission lines associated with this project traverse challenging terrain, spanning altitudes from 185.69 m to 2962.86 m, and are engineered to facilitate the evacuation of approximately 7.54 GW of electricity. This includes power generated from major hydropower projects such as Sunkoshi-2 (1110 MW), Khimti Shivalaya Storage HPP (1853 MW), Sunkoshi-3 (536 MW), and Dudhkoshi-2 Jaleshwor (240 MW).
The initial scope was expanded to cover Lamahi – Chhinchu 400 kV TL Project, a route spanning altitude range from 249.07 m to 1111.93 m and is aimed at enhancing the capacity of Nepal’s national grid. The new 400 kV line will provide essential infrastructure to evacuate power from upcoming generation projects, supporting the reliable transmission of electricity and strengthening the overall Integrated Nepal Power System (INPS).
Client : Nepal Electricity Authority (NEA)
Funding Agency : Asian Development Bank (ADB)
Scope of Works : Desk Study and Walkover survey,Detail survey of TL & S/S including plan and profiling, tower schedule, tower spotting and optimization,Geotechnical Investigation, Detailed Design of Transmission Line and Substation, Environmental and Social Study, Preparation of Technical Specification, Cost Estimates & Bidding documents, Economic & Financial Analysis, & Preparation of Detailed Project Report
Project Features under CP-1:Length: 135 km (approx.)Location: Solukhumbu, Okhaldhunga, Dolakha, Sindhuli, & Dhanusha Districts. Substations: 400/220 kV Bay Extension Tingla Hub SS, 400 kV Bay Extension at New Khimti SS,400/132 kV New Sunkoshi Hub SS, 400/132 kV Bay Extension Dhalkebar SS, Transmission Line: Section-1: Line connects Tingla Hub S/S with New Khimti S/S (55 km), Section-2: Line connects New Khimti S/S with Sunkoshi Hub S/S (40 kmz_x, Section-3: Line connects Sunkoshi Hub S/S with Dhalkebar S/S (40 km) Project Features under CP-1 Additional Scope : Length: 98.21 km (approx.) Location: Dang, Salyan, and Surkhet Districts Line connects 400 kV Lamahi S/S with 400 kV Chhinchu S/S