Transmission
Lines
Public Discussion during execution of Walkover Survey
The 400 kV and 132 kV transmission lines under this project are instrumental in enhancing the reliability and efficiency of Nepal’s power transmission network. They are designed to address the increasing electricity demand in key regions, including the Budhigandaki Basin, Sindhupalchowk, Kavrepalanchok, Ramechhap, as well as the remote districts of Dailekh, Kalikot, and Jumla. Jade Consult, in collaboration with POWERGRID Corporation of India Ltd., is contributing to this effort as part of a broader initiative to strengthen and expand the Integrated Nepal Power System (INPS).
The scope of Consulting Services under the CP-2 Project was expanded through an amendment to the Principal Contract, incorporating several key components. This extension includes the Engineering and Environmental Study for the New KhimtiRakathum and Phukot–Ranchuli 132 kV Transmission Line Projects. In addition, it covers substation-related works such as the 132 kV bay extensions at New Khimti and Kavre/Ramechhap substations, as well as at Kalikot and Phukot substations. The amended scope also includes the development of new 400 kV substations at Motipur, Lamahi, Chhinchu, and New Attariya, further strengthening the national transmission infrastructure.
Client : Nepal Electricity Authority (NEA)
Funding Agency : Asian Development Bank (ADB)
Scope of Works : Desk study and walkover survey,Detail survey of TL including plan and profiling, tower schedule, Tower spotting and optimization, Geotechnical investigation, Detailed Design of Transmission Line and Substation, Environmental and Social Study, Preparation of Technical Specification, Cost Estimates & Bidding documents, Economic & Financial Analysis, & Preparation of Detailed Project Report
Project Features under CP-2 : Length: 205.4 km (approx.), Location: Sindhupalchowk, Ramechhap, Dhading, Nuwakot, Gorkha, Dailekh, Kalikot, and Jumla Districts, Substations: 400/132/33 kV Pokhartar (Gumda) GIS SS, 132/33/11 kV Kavre/Ramechhap AIS SS, 132/33/11 kV Kalikot GIS SS, 132/33/11 kV Jumla GIS SS, Bay extension at 400 kV Ratamate GIS SS, Bay extension at 132 kV Lamoshangu AIS SS, Bay extension at 132 kV Dailekh AIS SS, Transmission Line: Section-1: 132 kV TL connects Lamoshangu S/S with – Kavre/Ramechhap S/S (38 km), Section-2: 400 kV TL connects Philim S/S with Gumda /S and with Ratamate S/S (85 km), Section-3: 132 kV TL Line connects Dailekh S/S with Kalikot S/S and with Jumla S/S (82 km)
Project Features under CP-2 Additional Scope: Length- 63 km (approx.) Location- Ramechhap District and Kalikot Districts, Substations: 400 (GIS)/220 (GIS)/132 (AIS) kV new GIS substation at Motipur as upgradation of existing 132/33/11kV Motipur substation, 400/220/132/33/11 kV New GIS substation at Lamahi, Chhinchu and Attariya (Daiji), Transmission Line: Section-1: 132 kV TL connects New Khimti S/S with – Kavre/ Ramechhap (Rakathum) S/S (28 km), Section-2: 132 kV TL Line connects Phukot S/S with Kalikot (Ranchuli) S/S and with Jumla S/S (35 km)