SASEC (South Asia Subregional Economic Cooperation) Power System Expansion Project
Client
Asian Development Bank
Implementing Agency
Nepal Electricity Authority (NEA)
Scope of Works (In association with POWERGRID India)
- Assist NEA in preparing designs, technical specifications and bidding documents
- Assist NEA in the bidding process and bid evaluation including preparation of technical and financial evaluation reports
- Assist NEA in contract negotiation with the contractor until contract awarded and advance payment paid.
Project Features
- Dana – Kusma 220kV transmission line (40 km length), and substations at Dana & Kusma
- Kusma – New Butwal 220kV transmission line (88 km length), and substation at New Butwal
- New Butwal – Bardaghat 400kV transmission line (45 km length), and LILO of 132kV Double Circuit Butwal- Bardaghat Transmission Line at New Butwal Substation.
- Markichowk- Matatirtha 220kV transmission line (82 km length), and associated substation at Markichowk extension at Matatirtha.
- New Bharatpur- Markichowk- Udipur 220kV transmission line (64 km length), and substation at Udipur, bay extension at New Bharatpur and Markichowk
- Udipur -Khudi-Manang 220kV transmission line (50 km length), and associated substations at Manang and bay extension at Udipur