Environment
& Social Studies
Plantation Area by the project
The Karmadev (Indo-Nepal Border) – Phukot (Kalikot) 400 kV Double Circuit Karnali Corridor Transmission Line and associated Substations Project is designed to evacuate power generated in the Karnali River Basin. The line originates from the Phukot Substation in Kalikot District, passes through the Betan Substation in Surkhet District and the Dododhara Substation in Kailali District, and terminates at Karmadev, where a cross-border connection with India is proposed. This transmission line will play a crucial role in integrating Karnali Basin hydropower into the national grid and facilitating power export through the Indo-Nepal border.
Client :Rastriya Prasaran Grid Company Limited
(funded by – Nepal Govt.)
Scope of Works :- Preparation of Initial Environmental Examination of all TL sections as per National Legislation, Preparation of Social Impact Assessment of all transmission sections as per ADB Requirement, Preparation of Tree Cutting Plan of all transmission sections
Project Features : Voltage Level for all sections: 400 kV, Right of Way of Transmission Line: 46 m (23 m right and 23 m left from center line), TL Section 1: Phukot-Betan 400 kV TL and associated Substation Project Length: 53.73 km, Affected Districts: 2 (Kalikot and Surkhet), SS to be constructedt: Phukot Substation, TL Section 2: Name: Betan-Dododhara 400 kV Transmission Line and associated SS Project, Length: 36.71 km, Affected Districts: 2 (Surkhet and Kailali), SS to be constructed: Betan Substation, TL Section 3: Dododhara-Karmadev 400 kV Transmission Line and associated Substation Project, Length: 29.6 km, Affected Districts: 1(Kailali), SS to be constructed under this project: Dododhara SS