SASEC (South Asia Sub-regional Economic Cooperation) Power System Expansion Project – Project Supervision Consultant
Client
Nepal Electricity Authority (NEA)
Job Details:
- Consulting Services for Project Supervision Consultant for different Subprojects under SASEC Power System Expansion Project.
Involvement (JV/Single):
- In association with Power Grid Corporation of India Limited
Project Features:
- Three (3) nos. of 220 kV Double Circuit and one (1) 132 kV Transmission Line Projects namely
- Kaligandaki Corridor TL Project (110 km) and 220 kV Substations at Dana, Kusma & New Butwal
- Marsyangdi Corridor TL Project (125 km), and 220 kV Substation at Markichok & 220 kV Substation Extension at Matatirtha
- Marsyangdi – Kathmandu TL Project (82 km), and 220 kV Substation at New Bharatpur, Udipur, Khudi and Manang
- Samundratar – Trishuli 3B Hub 132 kV TL Project
- Distribution System Expansion in Eastern, Central and Western Nepal
- Grid Substation Reinforcement Project
Project Activities:
a. Contract Signing of the Project:

b. The Soil Investigation works carried out in the project area of Dana – Kusma 220 kV Line.

Soil investigation works in progress at proposed Kushma Substation
c. Visit of the Consultant to proposed Samundratar Substation and fixing the tentative Alignment of Project road with reference to substation site and quarter area.

Site of Proposed 132 kV Samundratar Substation